What the Building Safety Levy means for property developers

Lewis Mulligan

Written by

Lewis Mulligan

Posted on
23 October 2026

Reading time
11 minutes

Share

The Building Safety Levy is a tax on new residential buildings in England, charged per square metre of floorspace on developments of ten or more homes (or 30 or more student bedspaces) where the building control application was made on or after 1 October 2026. For a developer, it means a new cost on the appraisal that changes with your postcode, a payment that has to clear before any home in the application can be signed off, and paperwork that applies even to schemes too small to pay anything.

What follows is how the levy works, what it costs on a typical scheme, and what to change in your appraisal and programme before your next site goes into building control.

Key points
  • The levy applies to schemes of ten or more homes, counted on the planning permission, where the building control application went in on or after 1 October 2026.
  • Rates are set by local authority, from £12.70 per square metre in County Durham to £100.35 in Kensington and Chelsea, and previously developed land pays half.
  • The whole levy for an application has to be paid before any home in it can be signed off, so it usually lands late in the build when your facility is most heavily drawn.
  • Schemes under ten homes pay nothing, but still have to file levy information or risk holding up sign-off.
In this article

The levy runs through building control, not planning

The levy exists to help pay for fixing historic building safety defects, such as unsafe cladding, and the government describes it as part of the funding that protects leaseholders from those costs. When amendments to the regulations were debated in the House of Lords in September 2026, the government said it estimates the levy needs to raise £3.4 billion, likely over ten years.

It was created by the Building Safety Levy (England) Regulations 2025, which came into force on 1 October 2026, and it applies in England only. Scotland has legislated for its own, separate levy, which applies to new homes completed from 1 April 2028.

The detail that catches people out is where it sits. The levy is collected by your local authority, but through building control rather than planning, and you pay the authority where the building stands whichever route you use, whether that’s the council’s own building control team, a registered building control approver or the Building Safety Regulator.

That’s also why the start date works the way it does. A building control application or initial notice submitted before 1 October 2026 sits outside the levy, and so do later variations to it. If that earlier application is rejected and resubmitted on or after 1 October, though, the resubmission is liable, so anything that went in during September is worth keeping clean.

Ten homes is the line, and your planning permission draws it

The levy only applies to what the regulations call a major residential development, which means ten or more new homes, or 30 or more bedspaces in purpose-built student accommodation. Anything smaller doesn’t pay.

The count comes from the planning permission, not from the building control application. You can’t bring a 50-home site under the threshold by submitting it in batches of seven, and the government’s own guidance gives a similar example, where seven homes on an estate with permission for 50 are chargeable.

A few other points worth knowing before you test your own pipeline:

  • Conversions count. Turning an office into 12 flats is chargeable even if the building’s footprint doesn’t change, because new residential floorspace is being created.
  • Affordable homes don’t reduce the count. A scheme of ten homes is major development even if some are social or affordable homes. Social and supported housing that meets the regulations’ definition isn’t charged, but it still counts towards the ten.
  • Extensions that create no new homes are outside the levy. If no new dwellings or student bedspaces are created, there’s no levy and no levy information to provide.
  • Joint ventures are only exempt if every partner is. The exemption for non-profit housing associations doesn’t pass to a joint venture unless every member qualifies.

The threshold also creates a cliff edge. Moving from nine homes to ten doesn’t add a tenth of the levy, it adds the whole thing, so the tenth home has to earn its share of the levy on all ten. If a site could go either way, have the levy in front of you when you and your planning consultant settle the unit numbers.

Your situationIs the levy charged?
Ten or more homes for open-market sale, building control application on or after 1 October 2026Yes
Fewer than ten homes on the planning permissionNo, but you still submit levy information
Seven homes on an estate with planning permission for 50Yes
An office converted into 12 flatsYes, even with no new footprint
Social housing as the regulations define it (most social rent, affordable rent and shared ownership, plus First Homes sold at no more than 70% of market value)No for those homes, with evidence. Other discounted homes are charged unless they meet that definition
Development by a non-profit housing association or its wholly owned subsidiaryNo
Care homes, hotels, hospitals, children’s homes and similar usesNo, they’re excluded
Building control application submitted before 1 October 2026No, unless it’s rejected and resubmitted

Your postcode sets the rate, and previously developed land halves it

The government has set a rate per square metre for every local authority in England, weighted by average house prices, so the most expensive areas pay the most. The rates run from £12.70 in County Durham to £100.35 in Kensington and Chelsea, and the full list sits in the GOV.UK table of levy rates.

The numbers that move an appraisal
£100.35
per m² in Kensington and Chelsea, the highest rate in England
50%
off the standard rate when at least 75% of the site is previously developed land
£61,000+
gap on ten homes between greenfield Barnet and previously developed Leeds

The rate is charged on the gross internal area of each new home, measured using the RICS Code of Measuring Practice. In a block of flats, the stairs, lobbies, landings, plant rooms and any residents-only facilities such as a gym are chargeable too. Where a communal area is shared with homes that are exempt, only a proportion of it is charged.

Sites that count as previously developed land pay half the standard rate. To qualify, at least 75% of the land inside the red line of the planning permission must meet the levy’s own definition, which is land that has had a building on it at any point since 1 July 1948. Fixed surface infrastructure such as roads, car parks, loading bays and pavements can count as buildings for this purpose. Land whose buildings are, or were most recently, used for agriculture or forestry doesn’t count, and nor do mineral workings, landfill, wholly underground buildings or unlawful operations. The test is applied on the date planning permission is granted, and the levy’s definition isn’t the same as the planning system’s definition of brownfield land. Schemes built under permitted development rights get the reduced rate automatically.

Here’s what that means for an illustrative scheme of ten homes at 120 square metres each, 1,200 square metres in total, with no communal areas and no exempt homes:

Local authorityStandard rate per m²Levy at standard ratePreviously developed land rate per m²Levy at reduced rate
Kensington and Chelsea£100.35£120,420£50.17£60,204
Barnet£63.35£76,020£31.68£38,016
St Albans£49.55£59,460£24.77£29,724
Bristol£42.97£51,564£21.48£25,776
Tunbridge Wells£39.25£47,100£19.62£23,544
Birmingham£29.23£35,076£14.62£17,544
Manchester£28.44£34,128£14.22£17,064
Leeds£24.57£29,484£12.29£14,748
County Durham£12.70£15,240£6.35£7,620

On the same ten homes, the difference between a greenfield site in Barnet and a previously developed site in Leeds is more than £61,000.

Small schemes don't pay, but they still have paperwork to file

This is the part small developers are most likely to miss. Any building control application or initial notice for one or more new homes has to include levy information, including how many homes it covers and whether it forms part of a major development. A council can reject a full plans application that leaves it out, and an initial notice without it must be rejected.

At the first commencement notice, you then have to show why no levy is due, usually with the planning decision notice confirming the number of homes. The council issues a notice of no charge, and when the works are finished you confirm that notice in a levy liability statement before the completion certificate can be issued.

For a seven-home scheme, the levy costs nothing. A missing form can still hold up sign-off on the homes your buyers are waiting to move into, which is an expensive way to save an afternoon of admin.

The bill lands before your first buyer moves in

Here’s how the process runs on a chargeable scheme:

  1. Building control application or initial notice. You give the initial levy information.
  2. First commencement notice. You give the floorspace figures, the number of exempt homes, whether the site qualifies for the reduced rate, and the evidence for each.
  3. Levy liability notice. The council issues the bill, or a notice of no charge, within five weeks, or eight if your information is selected for a spot check. Higher-risk buildings going through the Building Safety Regulator take seven weeks, or ten with a spot check.
  4. Payment. You can pay at any point after the notice arrives, but it must be paid before the building work is completed or the building is occupied, whichever comes first.
  5. Sign-off. The whole levy for an application has to be paid before a completion certificate can be issued for any of the works in it. The council confirms payment with a levy payment certificate within two weeks.

If you think the bill is wrong, you have 28 days to ask the council for a review, and if you disagree with the outcome, a further 28 days to appeal to the First-tier Tribunal.

The commercial point sits in step five. The levy usually has to be paid late in the build, when the development facility is heavily drawn and most of the sales money is still to come. If every home on a site sits under one building control application, the full levy for all of them has to be paid before the first home can be signed off, so how your applications are structured decides how much cash you need to find before your first handover.

Raising money for a scheme?
Lenders and investors will look for the levy in your appraisal. Book a discovery call and we’ll review your investor materials the way they will.

Your buyers won't pay the levy for you

It’s tempting to treat the levy as something you’ll add to the asking prices. In most markets that’s hard to do, because buyers compare your homes with the scheme down the road and the resales on Rightmove, and few will pay £4,710 more for a house in Tunbridge Wells because of a tax they’ve never heard of.

So in most cases, the levy comes out of your margin or out of what you can afford to pay for land. That makes the other costs you control matter more, and the largest of them is usually time. We made the same point in How Much Does It Cost to Market a Property Development?, where marketing done properly is funded within the development and exists to bring the sales forward. A levy paid before completion, followed by a facility still charging interest while the last homes sit unreserved, squeezes the same margin twice.

An appraisal that includes the levy shows you’ve done the work. One that leaves it out gives a lender or investor a reason to wonder what else is missing.

There’s an investor angle too. If you’re raising money for a scheme with a building control application made on or after 1 October 2026, expect investors and lenders to ask where the levy sits in the appraisal, and whether it’s at the right local rate and in the month it falls due. An appraisal that includes it shows you’ve done the work. One that leaves it out gives a lender or investor a reason to wonder what else is missing, and that doubt tends to show up in the terms they offer.

What to actually do about it

Most of this can be settled in an afternoon with your appraisal and your planning documents open:

  • Check the date on every building control application in your pipeline, and make sure nothing submitted before 1 October risks being rejected and resubmitted.
  • Count the homes on the planning permission, not on the application, to see whether each site crosses the ten-home line.
  • Look up your local rate in the GOV.UK table, and test whether at least 75% of the red line counts as previously developed land.
  • Measure gross internal area to the RICS Code, including any communal areas used by residents.
  • Gather exemption evidence early, such as the Section 106 agreement or a contract with a housing association, because it’s needed at commencement.
  • Put the levy in your cash flow in the month it’s payable, not just as a line in the appraisal.
  • Talk to your building control body about the levy forms and how your applications are structured across phases.
  • Update your investor pack and lender submissions so the levy is visible before anyone has to ask about it.

Frequently asked questions

The levy came into force on 1 October 2026. It applies to building control applications and initial notices submitted on or after that date, so schemes submitted before it are outside the levy unless the application is rejected and resubmitted.

The client named on the building control application or initial notice pays it, usually the developer. It’s paid to the local authority where the building is located, whichever building control route you use.

No levy is charged on developments of fewer than ten homes, or fewer than 30 student bedspaces, judged on the planning permission. You still need to provide levy information with your building control application and obtain a notice of no charge before the completion certificate can be issued.

Multiply the chargeable floorspace, measured as gross internal area in square metres, by your local authority’s rate. Chargeable floorspace includes the new homes and any communal areas their residents use, and excludes exempt homes such as social housing.

Yes. Sites where at least 75% of the land within the planning red line counts as previously developed land, using the levy’s own definition rather than the planning one, pay half the standard rate, and schemes built under permitted development rights get the reduced rate automatically.

Yes. Converting a non-residential building into ten or more homes is chargeable on the new residential floorspace created, even if the building’s footprint doesn’t change.

No. The levy applies in England only. Scotland has passed its own Scottish Building Safety Levy, which applies to new homes completed from 1 April 2028.

This post summarises the levy for developers and isn’t tax or legal advice. Check your own scheme with your building control body, quantity surveyor or solicitor before you rely on a figure.

Final thoughts

The Building Safety Levy won’t turn a good site into a bad one, but it changes the numbers around the ten-home line, the cash you need before your first handover and what an investor expects to see in your appraisal. Treated as a building control form, it shows up when the council sends the bill. Treated as an appraisal line, it shows up months earlier, while there’s still time to rethink the unit mix, the way your applications are structured or what you can pay for the land.

Before your next appraisal

If an investor opened your next appraisal tomorrow, would they find the Building Safety Levy already in it, at your local authority’s rate and in the month it falls due?

If you’re not sure, that’s the place to start.

Our investor packs are built to answer the questions investors ask before they ask them. For a second opinion on the materials you already have, book a discovery call and we’ll look at them the way an investor would, then tell you what we’d change, if anything.

Subscribe to our newsletter

Stay informed with the property branding world - No spam, just value!

In this article

Written by
Lewis Mulligan

Posted on
23 October 2026

Share

Property Branding
Privacy Overview

This website uses cookies so that we can provide you with the best user experience possible. Cookie information is stored in your browser and performs functions such as recognising you when you return to our website and helping our team to understand which sections of the website you find most interesting and useful. Please see our privacy policy for more.